In its decision rendered on November 12, 2026, the administrative court in Lille finally lifted the mortgage that weighed on the property.’Lille Airport For several years. The legal authority has asked the mayors of Lesquin and Fretin, neighboring communes to the airport, to issue the building permit within two months. Both communes had refused the authorization in 2022, notably due to noise nuisances.
The court held that these arguments did not justify the refusal of the permit, as issues related to air traffic and noise fall under other regulatory provisions. It also confirmed the validity of the environmental permit issued by the Prefect of the Nord.
An enlarged and completely reorganized terminal
The main component of the program concerns the transformation of the airfield, which was put into service in 1996. The current building, with an area of 18,000 m², is to be renovated and expanded to initially reach 33,400 m², according to the specifications presented by the contracting authority.
The goal is to better separate the flows of passengers arriving and departing today, which are currently concentrated in spaces that have become insufficient. Departures will be reorganized around the registration, security and boarding areas. Arrivals will benefit from new baggage delivery areas, dedicated halls and separate circuits for Schengen and non-Schengen travelers.
A new pier will also accommodate modular boarding areas, with four pre-boarding walkways. The shops and reception areas will also be redesigned.
The infrastructure on the runway side will also be subject to interventions. The program includes, among other things, the construction of shoulders for the main runway, the widening of the aircraft traffic lanes, the creation of an additional taxiway, and the extension of the aircraft parking area. However, it does not include either the lengthening of the main runway or the construction of a new runway.
The land access will be redesigned with the demolition of the current ramp and the covered parking lot located in front of the airport. A landscaped multimodal plaza is intended to facilitate connections between the different modes of transport.
An investment adapted to the prospects of traffic
The initial project represented an investment estimated at 100.9 million euros excluding taxes, of which 13.4 million were earmarked for upgrading and 87.5 million for modernization. Its financing was to be provided by the concessionaire Aéroport de Lille SAS, controlled by Eiffage.
However, the program was revised in September 2026 to take into account the evolution of traffic and restore the economic balance of the concession. The scope of the extension was reduced from 15,000 to 9,000 m². The concession was also extended for three years, until 2042. The updated amount of investments has not yet been officially specified.
However, there is one important element missing at the airport: an environmentally friendly service by public transport. Admittedly, two bus lines operate the shuttle service between the airport, Lille Centre and the «4 cantons» metro station for 15 to 20 minutes. But a direct tramway project was abandoned in 2025, the European Metropole de Lille (MEL). Estimated at 350 million euros, it was also rejected by the municipalities along the future line because it would not bring any benefits to the residents of the areas it would cross…
In 2025, Lille-Lesquin welcomed approximately 1.7 million passengers, which is 22.1% less than in 2019. The operator expects 1.8 million in 2026 and aims for between 3 and 3.5 million passengers by 2045.
For Lille and the Hauts-de-France, the judicial clearance therefore represents an important advance. The complex project now needs to be completed without interrupting the platform’s air traffic operations. The operator mentions a commissioning of the new facilities at the end of 2030 or the beginning of 2031.